New Office Network Checklist: From Floor Plan to Handover

Opening or relocating an office involves cabling, internet circuits, Wi-Fi, security and building rules that all run on different lead times. This checklist puts the network work in order, from floor plan review to handover.

Published
Updated
Reading
3 minutes
Prepared by
EngineSpire Technologies

Key points

  • Order internet circuits early; their lead times often decide the move-in date.
  • Review floor plans before fit-out so cable routes, the telecom room and access point positions are designed in.
  • Design the network before equipment arrives, and configure and test it off site.
  • Test everything before staff arrive: cabling, internet failover, Wi-Fi, printing, phones and applications.
  • Handover needs documentation: drawings, test results, configurations, credentials and support contacts.

1. Requirements

  • Headcount on day one and expected growth.
  • Desks, meeting rooms, training rooms and common areas.
  • Devices: laptops, desk phones, printers, displays, cameras, access control and sensors.
  • Applications and where they run: cloud, head office or a local server.
  • Security and compliance requirements for the business.
  • Budget and the target move date.

2. Building and site assessment

  • Building administration rules: work permits, accredited contractors, working hours and noisy-work restrictions.
  • Which internet providers already have fiber in the building, and how cables enter it.
  • Riser access, ceiling type and where access points can be mounted.
  • Power availability, backup power and cooling for the telecom room.
  • Site hazards such as flooding. For locations in the Philippines, GeoRisk Philippines' HazardHunterPH offers a free hazard assessment by location.

3. Internet and carriers

  • Request proposals from at least two providers as soon as the address is confirmed.
  • Ask about installation lead time, building entry, service levels and static IP addresses.
  • Choose a backup link from a different provider or technology.
  • Plan a temporary connection in case installation is delayed.
  • If desk phone numbers are moving, start number porting early.

4. Telecom room

  • A lockable room or cabinet with controlled access.
  • Ventilation or cooling for the equipment's heat output.
  • Dedicated power circuits, UPS and proper grounding.
  • Rack space for today's equipment plus growth.
  • Clear pathways for cabling to the floor and risers.

5. Structured cabling

  • Data outlets per desk, meeting room, printer and display.
  • Cable points for access points, cameras and access control, positioned from the Wi-Fi and security designs.
  • Category 6A for access points that use multigigabit ports; Category 6 is often enough for desks.
  • Permanent links within standard length limits.
  • Consistent labeling of outlets, panels and cables.
  • Certification test reports for every cable.
  • Spare capacity in pathways and patch panels.

6. Network design

  • IP address plan that does not overlap with other offices.
  • Network segments for staff, voice, printers, cameras, building devices and guests.
  • Firewall policy, remote access and site-to-site connectivity.
  • Predictive Wi-Fi design from the final floor plan.
  • Printer and wireless display discovery across segments.

7. Procurement and staging

  • Bill of materials with lead times checked against the schedule.
  • Configure and test equipment in a staging area before installation.
  • Update firmware, label devices and back up configurations.

8. Security

  • Administrator credentials stored in a password vault, with MFA where supported.
  • Logging from firewalls and network devices to a central system.
  • Physical security for the telecom room and network cabinets.
  • Guest Wi-Fi isolated from internal systems.

9. Installation and testing

  • Cabling certification results reviewed before equipment is installed.
  • Wi-Fi validation survey against the design.
  • Internet failover test with real applications running.
  • Printing, scanning, phones and meeting room systems tested.
  • Business applications tested by representative users.

10. Move and cutover

  • Stage the move by team where possible.
  • Provide on-site support on the first working days.
  • Decommission the old office network and sanitize storage in devices being retired.

11. Handover pack

  • As-built floor plans with outlet, access point and camera positions.
  • Cabling and Wi-Fi test reports.
  • Network diagrams, IP plan and device inventory with serial numbers and warranties.
  • Configuration backups.
  • Credentials handed over through a secure channel.
  • Provider contracts, circuit IDs and support contacts.

Common questions

How early should we order internet service for a new office?

As soon as the address is confirmed. Installation lead times vary by provider and building and may depend on building permits or new cabling into the building. Plan a temporary connection in case of delays.

Should we use Category 6 or Category 6A cabling?

Category 6A supports 10 Gigabit Ethernet over the full standard channel length and suits access points with multigigabit ports. Category 6 is often sufficient for desk connections.

Who should keep the network documentation after handover?

Your IT team or managed service provider should hold the as-built drawings, configurations, credentials and test results, stored securely and updated whenever something changes.

Sources and further reading

  1. [1]SP 800-153: Guidelines for Securing Wireless Local Area Networks — NIST
  2. [2]HazardHunterPH — GeoRisk Philippines